A fire scenario defines how the building responds to a fire: which systems start in a given zone, in what order and with what effect on evacuation and firefighting. We prepare it for buildings where a dozen or more installations have to act as one.
Basis
In the UK and the Middle East this logic usually sits in the fire strategy and its cause-and-effect matrix. In Poland it is a formal document: a fire scenario is required for every building that must have a fire detection and alarm system. The regulations on fire safety design review (Regulation of the Minister of the Interior and Administration of 5 August 2023) require it to be developed jointly by the designer and the certified fire safety expert (rzeczoznawca). The fire safety systems specified in the design must follow from the regulations and from the adopted scenarios.
A fire scenario is a description of the sequence of possible events during a fire that is representative of its location, in particular of a fire compartment or smoke zone. It covers the operation and interaction of fire safety systems, building services and process equipment, and the management measures needed for them to work properly.
Scope
Complex buildings
We specialise in buildings where a simple “fire alarm starts smoke extraction” is not enough. We have worked on metro infrastructure, the Świna tunnel, PGE Narodowy (the National Stadium in Warsaw), Tauron Arena and dozens of multi-storey car parks.
Stations, cross-passages and road tunnels, where smoke control, zoning and evacuation run in one multi-scenario algorithm.
Malls, retail areas, cinemas and car parks under one roof. Dozens of smoke zones and several smoke control systems at once.
Phased evacuation, people with reduced mobility, refuge areas and systems that have to run for longer periods.
Thousands of people, large volumes, smoke extraction from the auditorium and communication with event security.
Stair pressurisation, firefighting lifts, zoned evacuation and coordination with the BMS.
Jet fan and ducted ventilation, smoke zones, electric vehicle charging. We verify the scenario with CFD simulation.
Process
We review the architectural and MEP design, the zoning, the systems and the evacuation assumptions.
We define the design fire events for each zone and how the building responds to a fire.
Where smoke control performance or evacuation time is decisive, we confirm the assumptions with CFD simulation and evacuation analysis.
We write the scenario narrative and the cause-and-effect matrix in a form ready for the system designers and the integrator.
At handover we check that the systems operate according to the scenario, including with hot smoke tests.
We combine the scenario with CFD simulations, evacuation analysis and hot smoke tests. Where the design departs from prescriptive rules we also prepare a fire engineered solution.
FAQ
In Poland, yes, for buildings required to have a fire detection and alarm system. The regulations on fire safety design review require a fire scenario to be developed jointly by the designer and the certified fire safety expert (rzeczoznawca), and the selection of fire safety systems must follow from the adopted scenarios. In other jurisdictions the same content is typically part of the fire strategy and its cause-and-effect matrix.
In Poland the scenario is prepared jointly by the designer and the certified fire safety expert at the building permit design stage. At F&K it is developed by our team of certified experts and fire safety engineers, and we confirm the smoke control and evacuation assumptions with calculations and simulations.
The scenario describes the fire and the building’s response in words: what happens, in what order and why. The cause-and-effect matrix is the same logic written as a table, ready for programming the control panels and checking at commissioning. A large building needs both documents.
Ideally at the building permit design stage, before the disciplines select their equipment. A scenario drawn up after the fact forces changes to installations and delays handover. In complex buildings we update it at the technical design stage and before the acceptance tests.
The cost depends on the number of fire compartments and smoke zones, the number of systems and whether CFD verification is needed. We quote individually after reviewing the design.
Send us the design or a project description. We will define the scope of the scenario, the analyses needed and the timeline.